Brick and roof tiles finished but not washed



Brick work and Roof tiles finished , but not yet washed , looks nice and happy overall how the house came up

Wednesday, June 10, 2009

guttering finished , getting ready for roof tiles



Guttering finished last week and seen 2 guys getting ready for the Rooftiles to be laid

Sunday, May 31, 2009

Brick work finished but not washed




Finally brick work done , after 3 weeks of Rain

Sunday, May 10, 2009

Frame , Electrical , Plumbing done





Frame is pretty much up , Electrical work is done

Tuesday, April 28, 2009

Slab poured




Slab poured on monday 27/04/2009 ,looks pretty good , would give a clear picture after the frame and windows goes up on Monday 04/05/2009.

Monday, April 27, 2009

Waffle pods and Peiring Done for Slab





Happy to see that things are getting on its way for the construction of the house
I was suprise to see the slab frame , waffle pods & peiring was done on 23/04/2009 and been told that slab will be poured on 27/04/2009 which is already finished , but havent taken the photos

Wednesday, April 15, 2009

Excavation Done