Wednesday, June 10, 2009

guttering finished , getting ready for roof tiles



Guttering finished last week and seen 2 guys getting ready for the Rooftiles to be laid

Sunday, May 31, 2009

Brick work finished but not washed




Finally brick work done , after 3 weeks of Rain

Sunday, May 10, 2009

Frame , Electrical , Plumbing done





Frame is pretty much up , Electrical work is done

Tuesday, April 28, 2009

Slab poured




Slab poured on monday 27/04/2009 ,looks pretty good , would give a clear picture after the frame and windows goes up on Monday 04/05/2009.

Monday, April 27, 2009

Waffle pods and Peiring Done for Slab





Happy to see that things are getting on its way for the construction of the house
I was suprise to see the slab frame , waffle pods & peiring was done on 23/04/2009 and been told that slab will be poured on 27/04/2009 which is already finished , but havent taken the photos

Wednesday, April 15, 2009

Excavation Done


Something is happening on the land as promised by the Builder , Cant wait till the Slab is poured to see how the layout looks like

Tuesday, April 7, 2009

Land DEtails







This is how it looks like to start with and what we are aiming for in 5-6 Months